Update
The sound mat is installed on 3rd in preparation for gypcrete Saturday. Units are ready for paint early next week.
Thursday, August 11, 2016
Update
3rd floor insulation will be complete Saturday.
Drywall is starting to get hung.
Friday, August 5, 2016
Update
The exterior is moving. We have started to insulate the 3rd floor.