All of first floor walls are built. 





String line for curbs is being set in preparation of pouring curbs this afternoon. 










Monday, April 11, 2016

1st floor trusses

The first of 3 truss trucks has been delivered. We will swing the 2nd floor Next week Tuesday. 


Friday, April 8, 2016

Update

Both retaining walls are poured and stripped. 



Nearly all exterior walls are built and we are framing unit separation walls. 




Below is the view from the fitness room. 







Tuesday, April 5, 2016

Project Update

One of the retaining walls is poured and forms are stripped. We will pour the other side of the wall tomorrow weather permitting. 





About half of the exterior walls are built and about a third have been set up.