Wednesday, October 19, 2016

Monday, October 17, 2016

Exterior

The exterior of the building is getting wrapped up. Sidewalk and parking lot are also going in. 


Units

Units are starting to get wrapped up. 






Friday, August 26, 2016

Update

The sound mat is installed on 3rd in preparation for gypcrete Saturday. Units are ready for paint early next week. 




Thursday, August 11, 2016

Update

3rd floor insulation will be complete Saturday. 
Drywall is starting to get hung. 








Friday, August 5, 2016

Update

The exterior is moving. We have started to insulate the 3rd floor. 




Wednesday, July 13, 2016

Friday, July 8, 2016

Roof

The entrie roof is sheathes and half is now shingled. We should have the roof dried in by the end of the day. 






Thursday, June 30, 2016

Roof

The last section of roof trusses are being set. We will start roofing Wednesday next week. 


Tuesday, June 21, 2016

Thursday, June 2, 2016

Update

The parking garage floor is complete. We are going to pour the ramp to the garage this afternoon and will start pouring the parking lot tomorrow. 








Tuesday, May 24, 2016

Wednesday, May 18, 2016

Update

2nd floor exterior walls are built. Hallway and party walls are up. Preparing to swing 3rd floor trusses on Tuesday. Concrete stoops are being poured. 













Thursday, May 12, 2016